Forest Roads - Timeline

Forest Road Coordination in the MFRC Northeast Landscape GIS project - Timeline and Progress Report
 

Start Date (Planned)

Finish Date (Planned)

Task

Persons Responsible

Progress

March, 2000

April, 2000

Set up draft forest road coordination plan.

Northeast Landscape coordination working group

Completed

April, 2000

May, 2000

Get support from Forest Resoures Council and the Forest Partnership.

Coordination working group

Completed

May, 2000

June, 2000

Get information out to others and start plan (Internet site set up, and contacts made to convene county road committees).

Coordination working group and Forest Resources Council (FRC) staff

Completed

June, 2000

August 30, 2000

Road Committees look over project. Provide contact names, and input into road attribute table structure.

Road Committee Chairs

Completed

July 15, 2000

September 15, 2000

Contact GIS technicians. Get input on road attribute table structure.

FRC Staff

Completed

September 15, 2000

November 6, 2000

Convert/translate current GIS forest road data into the common forest road data structure.

GIS technicians from participating groups

Completed

September 18, 2000

November 16, 2000

Combine common forest road GIS data from each group into a draft GIS common forest road GIS layer.

FRC Staff

Completed

November 16, 2000

December 7, 2000

Provide data back to participating groups, and let them review it.

FRC Staff and participating groups

Completed

December 7, 2000

February 8, 2001

Convene road committees to look over data and provide input on future steps.

Road Committee Chairs

Completed

January 15, 2001

June 15, 2001

Update road GIS layer and produce final GIS dataset.

FRC Staff and road committees

Completed